November 22, 2023 by Katherine Seibt
-
-
Loxley, AL
-
-
This Planned Unit Development is comprised of over 4,300 acres situated between Loxley and Spanish Fort.
-
-
The Golden Triangel consists of 338 residential lots currently, with plans for thousands more over the course of the next several decades.
-
-
Builders: D.R. Horton and Truland Homes
Category: Comments Off on GOLDEN TRIANGLE
by Katherine Seibt
-
-
Spanish Fort, AL
-
-
Phases 1, 2, and 3 were developed for D.R. Horton, between 2012 and 2013, and consisted of 18, 19, and 39 lots respectively. Phase 4 was developed in May of 2016, for Holiday Builders and included 21 lots. The final 32 lots in Phase 5 were completed in May of 2018 for Truland Homes.
-
-
Grace Magnolias consists of 129 lots on 58 acres.
-
-
Builders: D.R. Horton, Holiday Builders & Truland Homes
Category: Comments Off on GRACE MAGNOLIAS
by Katherine Seibt
-
-
Orange Beach, AL
-
-
Construction for this townhome specific project was completed in June of 2018.
-
-
Gulf Stream consists of 64 lots on 11 acres.
-
-
Builder: D.R. Horton
Category: Comments Off on GULF STREAM
by Katherine Seibt
-
-
Cantonment, FL
-
-
Construction was completed in March of 2019.
-
-
Harmony Estates consists of 44 lots on 17 acres.
-
-
Builder: Truland Homes
Category: Comments Off on HARMONY ESTATES
by Katherine Seibt
-
-
Pace, FL
-
-
Phase 1 comprised 78 lots and was delivered in February of 2017. Phase 2 delivered an additional 47 lots in October of 2018. Construction of the third and final phase, which included 52 lots, was completed in August of 2019.
-
-
Hawks Landing consists of 177 lots on 45 acres.
-
-
Builder: D.R. Horton
Category: Comments Off on HAWKS LANDING
by Katherine Seibt
-
-
Fairhope, AL
-
-
Fairhope Falls West is a new section of the development in Fairhope Falls. It comprises an additional six phases and over 300 lots once complete. Construction on phase 4 (the first phase of this section, but the fourth phase overall in Fairhope Falls) began in February 2022 and delivered 38 lots. Phases 5, 6 & 7 were completed by December 2023 and consisted of 68, 70, and 60 lots respectively. Two more phases remain and they will deliver an additional 92 lots by June 2025.
-
-
Fairhope Falls West will consist of 328 lots on 149 acres.
-
-
The new phases will add a pool, clubhouse, playground, and recreation and exercise parks to the already existing amenities in Fairhope Fall.
-
-
Builder: D.R. Horton
Category: Comments Off on FAIRHOPE FALLS WEST
December 21, 2023 by Katherine Seibt
-
-
Spanish Fort, AL
-
-
Delivered in March 2023.
-
-
Fallingwater at Stonebridge will consist of 141 lots.
-
-
Amenities include a pool, clubhouse, dog park and pickleball courts
Category: Comments Off on FALLINGWATER AT STONEBRIDGE
November 22, 2023 by Katherine Seibt
-
-
Bay County, FL
-
-
Construction on phase 3 was completed in February 2018 and D.R. Horton purchased 50 lots on April 5th. The remaining 36 lots closed in April of 2019.
-
-
Phase 3 of Magnolia Hills consists of 86 lots on 32 acres.
-
-
Builder: D.R. Horton
Category: Comments Off on MAGNOLIA HILLS
by Katherine Seibt
-
-
Santa Rosa Beach, FL
-
-
Development was completed in Marc of 2018.
-
-
Miller’s Crossing Townhomes consists of 72 lots on 20 acres.
-
-
Builder: D.R. Horton
Category: Comments Off on MILLER’S CROSSING TOWNHOMES
by Katherine Seibt
-
-
Spanish Fort, AL
-
-
Phase 1 is made up of 31 lots and was completed in August of 2016. Construction on Phase 2 was completed late in October 2018 and delivered another 20 lots.
-
-
Osprey Ridge consists of 51 lots on 23 acres.
-
-
Builder: Truland Homes
Category: Comments Off on OSPREY RIDGE